Door Gate Installation Instruction Sheet

Eco Gates

The gate can be installed inside the casing of the door or outside the door, see above. It will pivot out of the way when not in use. The gate can be mounted on the left or right. Simply turn the gate upside down to mount on the opposite side.

  1. Stand Folded gate against the doorframe where you intend to mount it.
  2. mark the mounting surface throught the holes in the hinge bar with a pen or pencil.
    For mounting into:
    • Wood: use 5/16" x 2" Lag Bolts
    • Steel: drill and tap for 5/16" x 1" Bolts.
    • Brick or Concrete: 5/16" x 2" Lag Bolts in 3/8" holes with lead anchors
  3. Drill appropriate size holes in the mounting surface.
  4. Mount the gate by inserting the screws through the hinge bar.
  5. Stretch the gate across the opening. Line up the locking bar with a pen or pencil.
  6. Mark through the mounting holes of the locking bar with a pen or pencil.
  7. Drill holes and insert the screws to mount the locking bar.
  8. Pull the door into the locking bar, and insert a padlock.
Warning: Consult life safety codes and/or local authorities regarding proper use of this product.



Single Gate Installation Instruction Sheet

Single Folding Gates

  1. Mark center of hole on floor 2" away from wall to fit 5/8" pin at bottom of gate.
  2. Drill 3/4" hold in floor.
  3. Place washer on 3/4" hole.
  4. Put gate in washer and hole.
  5. Install "L" bracket on wall.
  6. Stretch gate to other side and install locking bar.

Warning: Consult life safety codes and/or local authorities regarding proper use of this product.


Gates can be installed on Casing or Facing.




Double Gate Installation Instruction Sheet

Double Folding Gates


Gates can be installed on Casing or Facing

  1. Mark center of hole on floor 2" away from wall to fit 5/8" pin at bottom of gate.
  2. Drill 3/4" hole in floor and place 5/8" washer over hole.
  3. Put bottom pin of gate in washer and hole.
  4. Install "L" bracket on wall, into...
    • Wood: Use 5/16" x 2" Lag Bolts
    • Steel: Drill and tap for 5/16" x 2" Bolts.
    • Brick or Concrete: 5/16" x 2" Lag Bolts in 3/8" holes with lead anchors.
  5. Repeat for opposite side.
  6. Stretch gates to center and drill 3/4" hole for center drop pin.


(Note: For installation outboard of ovberhead door side rails, ask for extended "L" brackets.)

Warning: Consult life safety codes and/or local authorities regarding proper use of this product.




Portable Gate Installation Instruction Sheet

Portable Folding Gates

  1. Remove packaging
  2. Install axles with wheels using hardware supplied
  3. Stretch gates across opening
  4. Mount Locking bars to wall with appropriate mounting hardware such that hole in outside rail lines up with locking hasp in Locking Bar


Warning: Consult life safety codes and/or local authorities reguarding proper use of this product.